In these times of uncertain supply chain delivery, AGC East Tennessee's Subcontractor Committee has created a quick cheat sheet for members to share estimated lead times on materials. Please note that these lead times are subject to change. If any member would like to add or edit information, please mail leslie@agcetn.org.
AS OF APRIL 18, 2022 Plumbing:
Brick:
CMU:
Mortar and Grout:
Masonry Accessories:
Bar joists: Bar joists continue to be between 45-50 week delivery ARO. Decking: 10 -12 week delivery if no bar joists are required, but longer lead times if delivered with bar joists. Steel Primer: Basic grey and red primer are in short supply due to a recent fire at a paint pigment plant. It has affected some deliveries by 1-3 weeks according to the product. We are sometimes using a premium product passed along to the GC/owner. The following have seen 50% + the past 2 years: